We’re operating based on the following schedule. The timetable and execution may be influenced by political decisions and the permitting processes required for port operations and expansions.

Current permit issues

• Zoning plans (Norrköping Municipality)
• Water permits (Norrköping Municipality)
• Operating permits (Norrköpings Hamn AB)
• Building permits

2023-2025

• Dismantling and reconstruction of Quay P8 with integrated section for heavy goods
Completion of construction works at the Pampus Terminal
Commissioning of the new quay and port area

2021-2022

Contractor work on the quay and port area begins
• Electrical system and other contractor work commences

2020

Completion of dredging contractor works
• Initiation of contractor works for quay and port area
• Preparation of specifications for electrical systems