The dredgingwork at the Pampus Terminal for better basins and longer quay started in November 2019.
From the middle of December the work will proceed with underwater drilling and blasting.

Arrivals and departures will be sceduled by the harbourmaster so that they won´t
collide with blasting procedures.The underwater drilling and blasting will be ongoing until 31st of March and
start again in October and end in January 2021.
Blasting will be ongoing up to three times a day between hours 07.00- 23.00, just outside berths P6-P10.
The blastings will be made underneath the water and can be felt as vibrations and heard as a rumbling boom.